Mercury Spill Cleanup

Location: Southeastern, WI

Project Summary:

North Shore Environmental Construction provided emergency response services for a large mercury spill at an industrial transportation facility located in southeastern WI. Mercury spill response and clean-up is a specialty service provided by North Shore. The spill and decontamination of the facility was successfully cleaned up utilizing sophisticated air monitoring and specialized mercury remediation equipment and mercury decontamination procedures developed by North Shore. Impacted areas were decontaminated and cleared for re-occupancy. Mercury contaminated waste was packaged, transported and disposed of at a hazardous waste disposal facility. Approximately 10-15 lbs. of elemental mercury was recovered. The project took three weeks to complete.

Project completed for an Industrial facility.