Industrial Services

Location: Kenosha, WI

Project Summary:

North Shore Environmental Construction completed the decommissioning (cleaning, removal & closure) of approximately 120 Chemical AST’s and process piping and process equipment including four reactors. The tanks ranged in size from 18,000 gallons to 45,000 gallons. North Shore utilized their own high pressure steam cleaning and specialized tank cleaning equipment. The project took approximately seven months to complete successfully.

Project completed for a Chemical Manufacturing facility.